"We want to catch the energy going over our land
and sell it into the grid," explained Dan Mazier,
head of non-profit Elton Energy Co-op.
What's different about this wind project from
others is profits wouldn't sail away to
multinational head offices. Instead, monies
would be windsocked back into the community, in
this case the RM of Elton, just north of Brandon
across the Trans-Canada Highway.
"If this flies, it will be the first in North
America," said Mazier, a grain and livestock
farmer in the area.
The idea of "keeping the profits at home" is
as old as farmer grain co-ops, now blowing in
the wind, and the Canadian Wheat Board -- three
generations of relative farmer solidarity under
threat now from the Harper government.
The math for Elton Energy Co-op goes
something like this: wind power plus people
powerequals community benefits.
The group hopes to build a single wind
turbine for $5 million, capable of generating 2
megawatts of power. That's enough to power about
1,500 homes, Mazier said.
Mazier doesn't know how profitable Elton's
wind turbine could be but he's seen where
existing wind turbines are netting $300,000 to
$350,000 each per year, before debt payments.
In other words, "windustry," as it's being
called, is big business. In Manitoba, 17 wind
developers recently filed 84 proposals for wind
farms costing hundreds of millions of dollars
each to build. Manitoba Hydro has shortlisted
the proposals down to 10.
"There's money somewhere," opined Mazier.
Most of the wind developers are
multinationals with Canadian head offices in
urban centres like Calgary and Toronto.
"It's ingrained in all of us that big
business knows what it's doing. I think there's
a lot more opportunity for rural Manitoba if we
take control of renewable resources ourselves,"
Mazier said.
Instead of a string of turbines, which can be
eyesores and result in resident complaints,
Elton Energy plans to put up just one.
"Do we want 50-to-60 turbines? Or do we want
just one or two?" said Mazier.
It's been a lot harder to pull off than
expected, with all the engineer, design,
environmental and feasibility studies required,
plus the development of a system people can
invest in, and figuring out land leases.
The return to investors has not been
determined but might be similar to Manitoba
Hydro Bonds, whose returns vary greatly
depending on the series but have been in the
five-to-seven per cent range.
At the very least, Elton Energy is creating a
template for other communities to follow to
build their own wind turbine, Mazier said.
The federal Co-op Development Initiative has
put up $50,000 for a feasibility study, and the
RM another $3,500. The project will have to
raise about $2.5 million from investors to buy a
wind turbine, "and the rest you borrow from the
bank."
Turbine manufacturers require that 90 per
cent of the money is paid upfront before
construction, and there is a two-year waiting
list.
"ö"ö"ö
Speaking of solidarity, tiny Pilot Mound
doesn't stand a chance of winning the title of
Hockeyville if Manitobans don't show some
solidarity.
This isn't just home boosterism. These folks
really deserve to win but won't because they're
the smallest community -- unless we support
them. A winner is determined based on judging
and the number of online votes.
There are five finalists up for CBC's title
of Hockeyville: Kingsville, Ont. (19,200
people); Glace de Roberval, Que., (10,800); Port
aux Basques, Newfoundland (4,600) and Pilot
Mound (630).
Wilcox, Sask. is the other entry with 250
people but that doesn't include 350 students at
its vaunted private hockey school, Notre Dame
College. Include those students and their
families and graduates through the years, and
that's a much bigger contingent.
Actually, Wilcox would be a very deserving
winner if Pilot Mound wasn't more deserving.
Notre Dame College is a great hockey factory,
producing stars like Vincent Lecavalier, Brad
Richards, Wendel Clark, and Rod Brindamour.
But it's not as great an accomplishment as
what people in Pilot Mound have done. They have
almost completed construction of a
state-of-the-art hockey arena with virtually all
volunteer labour. It's taken them eight years.
The frame came from tearing down Manitoba
Hydro's temporary rec centre for hydro dam
workers at Sundown, 12 hours north of Pilot
Mound. In a span of 40 days, Pilot Mound
volunteers tore down the rec centre and moved it
to their community.
They've been putting it back up ever since,
with many modifications. Contractors were hired
to supervise volunteers where expertise is
needed, but otherwise all the work has come from
unpaid dreamers. |